Our Largest Plant to Run Extra Production

The company and Works Council 
have agreed on the 
following mode 
of operation for production
in Wolfsburg and the
 following special measures for 
the second quarter of 2018 and plant holidays.



Special measures in 
Production 1 and 2 and 
the adjacent divisions in 
the second quarter 
of this year:

 

Production 1  – assembly lines 2 
and 3, 
body shop, paint shop and 
adjacent divisions:

  • Saturdays on early shift on May 26, 
June 2, June 9, June 16 and June 30.
  • Sunday on night shift on June 24.

 

Production 1 – assembly line 1, 
some parts of paint shop, car completion and adjacent divisions:

  • Saturdays on early shift on June 9 and June 16.
  • Sunday on night shift on May 13.

 

Production 2 – assembly line 4, 
paint shop, body shop window 3 and adjacent divisions:

  • Sundays on night shift on June 10 and June 17.

 

Body shop window 4:

  • Saturdays on early shift on June 9 and June 16.
  • Sunday on night shift on May 13.


The special shifts mentioned above also apply to Logistics and the Wolfsburg Plastics business segment, according to a notice.

Business Unit Chassis Wolfsburg:

     

  • 
Saturdays on early shift on May 12, 
May 26, June 2, June 9, June 16, 
June 23 and June 30.

  • Sundays on night shift on May 13, 
May 27, June 3, June 10, June 17, 
June 24 and July 1.

Special measures in July 
for the plant holidays 
in Wolfsburg:

 

Production 1 – assembly line 1,
some parts of paint shop, body shop window 3, car completion and adjacent divisions:

  • Saturdays on early shift on July 14 and July 21.
  • Early and night shift each extended by two hours for production in calendar weeks 28, 29 and 30.

More details on the blackboards in the Wolfsburg plant.